Ørsted starts offshore construction of 920 MW offshore wind farms in Taiwan

Feb 18, 2025

Ørsted now commences the offshore construction for the Greater Changhua 2b and 4 offshore wind farms in Taiwan. The landmark project will deliver 920 MW of clean energy, which significantly contribute to Taiwan’s energy transition goal.

Ørsted was awarded the 920 MW Greater Changhua 2b and 4 offshore wind farms in June 2018. In July 2020, Ørsted signed a 20-year fixed-price corporate power purchase agreement (CPPA) for a corporate customer to offtake the full production of the wind farms.

Per Mejnert Kristensen, President of Region APAC at Ørsted, says: "The commencement of offshore construction for the Greater Changhua 2b and 4 demonstrates Ørsted’s unwavering commitment to developing, constructing, and operating large-scale offshore wind farms in Taiwan.”

Greater Changhua 2b and 4 offshore wind

He continues: “As the first offshore wind farms in Taiwan backed by a CPPA, they not only demonstrate the confidence our customer and the market have in Ørsted’s industry-leading technical expertise and extensive experience but also set a significant benchmark for long-term partnerships between businesses and the industry for renewable energy as well as the vital role of offshore wind in building a low-carbon economy.”

Since its final investment decision in March 2023, Ørsted has begun the manufacturing of the key components, completed civil work of the onshore substation, and started mobilising vessels to prepare the offshore construction.

The Greater Changhua 2b and 4 offshore wind farms are expected to complete offshore installation by the end of 2025 and be fully connected to the grid in 2026. Once completed, Ørsted will reach a combined operational offshore wind capacity in Taiwan of nearly 2 GW, producing clean energy enough to power two million Taiwanese households.

Ørsted currently has 9,9 GW of operational offshore wind capacity installed across three continents, with an additional 8,4 GW of offshore wind under construction.

Facts about Greater Changhua 2b and 4

• Capacity: 920 MW.

• Location: 35-60 km off the coast of Changhua County, Taiwan.

• Water depth: 23.8-44.1 m.

• Size of the wind farms: 185 km2.

• Wind turbine capacity: 14 MW (66 Siemens Gamesa 14-236 DD).


Key milestones

• Project awarded: June 2018.

• Final investment decision: March 2023.

• Onshore substation construction kick-off: April 2023.

• Offshore construction begins: February 2025.

• First power: Expected in Q3 2025.

• Offshore installation: Expected to be completed by the end of 2025.

• Full grid connection in 2026.

Similar Stories

https://www.ajot.com/images/uploads/article/POLB_Signingjpg.jpg
DOT and Port of Long Beach sign agreement to test nuclear-powered vessels
View Article
SPIRO publishes its first Sustainability Report

SPIRO published its inaugural Sustainability Report.

View Article
https://www.ajot.com/images/uploads/article/Anemoi_s_production_facility.png
Latest Bureau Veritas approvals strengthen confidence in Anemoi Rotor Sail technology
View Article
https://www.ajot.com/images/uploads/article/01_-_Arc_Tug_Render_01.jpg
Arc joins the Maritime Battery Forum
View Article
https://www.ajot.com/images/uploads/article/Houthi_threats_07-20.jpeg
2.5 million bpd of Saudi oil at risk as Houthis threaten to enact naval blockade – Rystad Energy market note
View Article
https://www.ajot.com/images/uploads/article/Cadeler_takes_delivery_of_11th_vessel-_Wind_Ace.jpg
Cadeler takes delivery of 11th vessel: Wind Ace
View Article