Megalift transporting for Tanjung Bin power plant since 2004

Apr 28, 2022

Megalift was the Turnkey Project Logistics Solutions provider for Phases 1, 2 and 3 of the Tanjung Bin Power Plant (2004-2006) and Phase 4 for the Power Plant in 2010.

Last month they were back in Tanjung Bin with a new transformer:
"We arranged the freighting of this 265-ton cargo from India to Jurong Port, Singapore. In Jurong Port, we performed a double banking to discharge the cargo onto a barge from the vessel."

Cargo

Dimensions

Weight

Transformer

6.10 m (H) x 5.20 m (W) x 5.30 m (H)

265 t

The barge then sailed to Tanjung Bin Power Plant's in-house jetty where Megalift rolled it off to transport the transformer to its final delivery point. This option was chosen as in-land transport was unfeasible due to the cargo’s weight.

At the site, Megalift also performed the jacking and skidding to move the transformer onto its foundation.

Similar Stories

https://www.ajot.com/images/uploads/article/AAL_wind_turbine_blades.png
AAL reduces sailings and boost efficiency for King Rocks Wind Farm
View Article
https://www.ajot.com/images/uploads/article/Ocean_Infinity_operations_centeer.jpg
Offshore operations: Why small improvements no longer cut it?
View Article
https://www.ajot.com/images/uploads/article/AAL_Brisbane_BESS_Cargo_A-Class%2C_AAL_Brisbane_loading_BESS_Cargo_in_Taicang.jpg
AAL Shipping claims 2026 AFLAS Project Cargo Award
View Article
https://www.ajot.com/images/uploads/article/TM3x.png
Total Movements manages heavy-lift gas processing units for Middle East gas production project
View Article
https://www.ajot.com/images/uploads/article/JSI_-_Dahej_berth_expansion-Jumbo_Javelin_%285%29.jpg
JSI Alliance delivers safe and efficient heavy-lift installation for Dahej berth expansion
View Article
https://www.ajot.com/images/uploads/article/790-Sander-Van-De-Meer.jpg
Logistics players adapting to Europe automotive industry’s shift in dynamics
View Article