Express Global Logistics (EXG),  member to the Worldwide Project Consortium (WWPC) in India, executed a complex long distance transportation for a major Power Electrical Equipment manufacturer from Karjan, Gujarat, to the Tyada station, Andhra Pradesh covering a distance of 1800 km.

The cargo to be transported consisted of a transformer measuring L- 4.8 (m) x W- 2.6 (m) x H- 3.4 (m) weighing 45 ton, 97 oil barrels and a Nitrogen Injection Fire Protection System (NIFPS). 

The project was very challenging as the cargo was transported on 6 axles over a distance of 1773 km initially. Movement beyond that was restricted due to the ghats.

Another challenge occurred 25 km before Srungavapukota (Skota) station as the main unit had to wait for 3 days for all the accessories to arrive and be offloaded in order to facilitate seamless rail movement through a single and narrow approach road only 3.5m wide. The entire consignment had to be manually offloaded from the axles, trucks and trailers and a 40 m dragging operation was put into place for loading the cargo on a ramp and eventually on a wagon at Skota station, Andhra Pradesh. Multiple railway shut downs were managed to successfully load and unload the consignment on/off the railway wagons. 

The EXG team had to carefully navigate the last leg of the rail movement covering 23 km through 13 tunnels by securing the cargo and keeping its height in check. 

Despite unstable climatic conditions, all safety measures were adopted to ensure the timely delivery of the cargo successfully to the site.

Similar Stories

https://www.ajot.com/images/uploads/article/EXG33.jpg
Express Global Logistics transporting ODC columns in India
View Article
https://www.ajot.com/images/uploads/article/AAL_Houston.png
AAL Shipping strengthens U.S. power sector support with Houston delivery
View Article
https://www.ajot.com/images/uploads/article/FPSO_Skid.png
XLP member, Manuport Logistics executes complex FPSO oil & gas skid transport operation
View Article
https://www.ajot.com/images/uploads/article/kasper_heiselberg_deugro.jpg
deugro appoints Heiselberg as President, Global Wind and Renewable Energy (GWRE)
View Article
https://www.ajot.com/images/uploads/article/Brandy_Aurich_photo.jpg
Blue Water appoints Aurich as Global Head of Commercial, Projects
View Article
https://www.ajot.com/images/uploads/article/20260529_Damen_LUV_010.jpg
Damen delivers Landing Utility Vessel 2208 to Blueshell Mussels
View Article