DOT awards contract on the I-40 Hernando DeSoto Bridge repair

May 18, 2021

Tennessee Department of Transportation Commissioner Clay Bright announced today the emergency bridge repair project has been awarded to Kiewit Infrastructure Group. The selection was based on qualifications, experience, and availability of personnel and equipment. The contractor is expected to start work as early as Wednesday.

The repair will be performed in two phases. Both phases will need to be completed before traffic can re-open on the bridge. At this point, we are unable to project a re-opening date. 

Phase 1 will require the installation of steel plates on each side of the fractured member. This repair will strengthen the damaged steel plates providing stability needed for crews to install equipment for the permanent replacement of the damaged components and continue bridge inspections. The design of the plates has been completed, and plans were provided to Stupp Bridge Company in Bowling Green, Kentucky, for fabrication. Fabrication of the roughly 18,000 lbs. of steel is expected to be complete by Wednesday, May 19th. TDOT forces will be picking up the fabricated plates from Stupp Bridge Company and transport them to Memphis, where they will be ready for the contractor.

Phase 2 design is underway and will be finalized with the input of the contractor. This will enable us to remove and replace the damaged piece and open the bridge to traffic.

Governor Bill Lee and TDOT Commissioner Bright will visit Memphis tomorrow.

Similar Stories

https://www.ajot.com/images/uploads/article/CROWN-X-Driver.jpg
CrownX | Driver app wins business for air freight trucking firms
View Article
https://www.ajot.com/images/uploads/article/Tom.JPG
Southeastern Freight Lines appoints Tom Henrici to Service Center Manager in Raleigh, North Carolina
View Article
https://www.ajot.com/images/uploads/article/Hactl_wins_2026_TIACA_Air_Cargo_Sustainability_Awards.jpg
Vanishing capacity is finally turning the tide on the freight recession
View Article
https://www.ajot.com/images/uploads/article/AARailroad.jpeg
AAR launches Freight Rail Research Consortium to advance research and policy
View Article
https://www.ajot.com/images/uploads/article/Landstar_Class_of_2025_Million_Mile_Safe_Drivers_and_Roadstars.jpg
Landstar honors top independent owner-operators at 2026 BCO All-Star Celebration
View Article
https://www.ajot.com/images/uploads/article/AARailroad.jpeg
AAR reports rail traffic for the week ending July 11, 2026
View Article