TC Energy dives as LNG pipeline is hit with higher costs again

TC Energy Corp. warned of higher costs for its Coastal GasLink pipeline, adding another financial hurdle for a project that will supply Canada’s first major liquefied natural gas export plant.

Wage increases, a shortage of skilled labor and disputes with contractors have contributed to a “material increase” in the cost of building the pipeline that will run from gas fields in eastern British Columbia to the coastal port of Kitimat. Management will give a new cost estimate early next year and its funding requirements will also rise, the company said in a statement Tuesday.  

TC Energy fell 4.5% to C$62.42 at 11:22 a.m. in Toronto, the biggest drop since Sept. 23. 

The pipeline, which will feed the Shell Plc-led LNG Canada plant, has been plagued by higher expenses because of construction delays caused by Covid-19 and protests. In July, TC Energy raised the estimate by 70% to C$11.2 billion ($8.2 billion). 

Calgary-based TC Energy had been locked in a dispute with LNG Canada over who would pay for the rising costs and threatened last year to suspend some construction activities as the two sides quarreled. The cost estimate in 2018 was C$6.2 billion. 

Coastal GasLink is now 80% complete and is still on schedule to be finished by the end of 2023. TC Energy said it’s looking to recover some costs from contractors. 

The LNG Canada project has been billed as the largest private-sector construction effort in Canada’s history, with a potential total investment of about C$40 billion ($29.4 billion) in the liquefaction plant, pipeline and gas drilling.

Bloomberg
Bloomberg

© Bloomberg
The author’s opinion are not necessarily the opinions of the American Journal of Transportation (AJOT).

Similar Stories

https://www.ajot.com/images/uploads/article/FAT_CMB.Tech_.jpg
WinGD achieves next ammonia milestone with first X72DF-A engine approval
View Article
Shell Plc first quarter 2026 Euro and GBP equivalent dividend payments

The Board of Shell plc announced the pounds sterling and euro equivalent dividend payments in respect of the first quarter 2026 interim dividend, which was announced on May 7, 2026…

View Article
https://www.ajot.com/images/uploads/article/Maersk_Gothenburg.png
CORE POWER, Maersk, LR and the Port of Rotterdam publish study on port calls for nuclear ships
View Article
https://www.ajot.com/images/uploads/article/GW-Sofia-Offshore-Wind-Farm-in-the-UK-North-Sea.jpg
Cadeler completes final turbine installation at Sofia Offshore Wind Farm
View Article
https://www.ajot.com/images/uploads/article/TIE06122026.jpg
Largest wind farm in the United States starts commercial operations
View Article
https://www.ajot.com/images/uploads/article/South_Asian_demand_keeps_pushing_coal_flows_higher_1.png
Signal Ocean: South Asian demand keeps pushing coal flows higher
View Article